New subsea cable set to be installed between Bute and Cumbrae

Bell Bay, Great Cumbrae

Scottish and Southern Electricity Networks (SSEN) has been granted a marine licence to replace one of the two subsea power cables connecting Bute and Cumbrae. 

The works, which are due to start early February and are expected to take a month to complete, will see a new cable installed between Kerrylamont Bay in Bute and Bell Bay in Cumbrae.


Ahead of the new cable’s arrival, preparatory works on Cumbrae are well advanced with similar work starting on Bute soon. The subsea installation programme in February will have no impact on electricity supplies in the local communities.


Deborah Young, SSEN’s Marine Consents Manager, said: “This essential project is part of our ongoing commitment to deliver the best possible service to our customers, and will go a long way to providing a safe, secure and reliable electricity supply across these local communities for many years to come.”


Around 90km of submarine cables connecting Scotland’s island communities will be replaced during the current Ofgem price control period (RIIO- ED1), which runs from 2015-2023. For more information, please visit www.ssen.co.uk/submarinecables.

The above image shows Bell Bay in Cumbrae.

 

 

 

About the author

Van on rural road

Scottish and Southern Electricity Networks

We're responsible for maintaining the electricity networks supplying over 3.8 million homes and businesses across central southern England and north of the Central Belt of Scotland. We own one electricity transmission network and two electricity distribution networks, comprising 106,000 substations and 130,000 km of overhead lines and underground cables across one third of the UK. Our first priority is to provide a safe and reliable supply of electricity to the communities we serve in Scotland and England.

Read more articles by Scottish and Southern Electricity Networks